Monthly Archives: April 2016

Mt. Rushmore Rd Project Update 2016-04-27

Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Wednesday, April 27 – Storm Sewer installation continues along Mt. Rushmore Road between Kansas City Street and Columbus Street. As weather permits, roadway grading will begin the week of May

Posted in Uncategorized

Mt Rushmore Rd Project Update 2016-04-21

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Thursday, April 21 – Storm Sewer installation continues along Mt. Rushmore Road between Kansas City Street and Columbus Street. As weather permits, roadway grading

Posted in Uncategorized

Pickup Location Moved

Mt. Rushmore Road Reconstruction Special Business Access The off-site parking/pickup area has been relocated to the west side of the Rushmore Plaza Civic Center between Lots C and D adjacent to Mount Rushmore Road and directly across from Central High

Posted in Uncategorized

Mt. Rushmore Rd Project Update 2016-04-14

Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Thursday, April 14 – Pavement removal is complete from Kansas City Street to Clark Street and is on hold until utility work catches up.  Water and Sewer work in

Posted in Uncategorized

Mt. Rushmore Rd Project Update 2016-04-07

Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Thursday, April 7 – Removal work is completed from Kansas City Street to Quincy Street and is continuing to move south along Mt. Rushmore Road. Sewer work is being

Posted in Uncategorized