Monthly Archives: September 2016

Mt. Rushmore Road Update 2016/09/29

FOR IMMEDIATE RELEASE Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Thursday, September 29, 2016 – Beginning Tuesday, Oct. 4, motorists can expect the South Street intersection to be closed for grading and gravel installation west of

Posted in Uncategorized

Mt. Rushmore Road Update 2016/09/28

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Wednesday, September 28, 2016 – Work continues on Mt. Rushmore Road and the adjacent side streets. On the west side of Mt Rushmore

Posted in Uncategorized

Mt. Rushmore Road Update 2016/09/22

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Thursday, September 22, 2016 – Work continues on Mt. Rushmore Road and the adjacent side streets. On the west side of Mt Rushmore

Posted in Uncategorized

Mt. Rushmore Road Update 2016/09/14

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Wednesday, September 14, 2016 – Work continues on Mt. Rushmore Road and the adjacent side streets. On the west side of Mt Rushmore

Posted in Uncategorized

Mt. Rushmore Road Update 2016/09/07

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Wednesday, September 7, 2016 – Work continues on Mt. Rushmore Road and the adjacent side streets. Surfacing work continues this week on the

Posted in Uncategorized

Mt. Rushmore Road Update 2016/09/07

FOR IMMEDIATE RELEASE Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Wednesday, September 7, 2016 – A shift in traffic on Mt. Rushmore Road, between South Street and Saint James Street, is scheduled for Friday, September 9.

Posted in Uncategorized

Mt. Rushmore Road Update 2016/09/01

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Thursday, September 1, 2016 – Work continues on Mt. Rushmore Road and the adjacent side streets. Surfacing work continues this week on the

Posted in Uncategorized