Mt. Rushmore Road Update 2016/10/26

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Wednesday, October 26 2016 – Work continues on Mt. Rushmore Road and the adjacent side streets. On the west side of Mt Rushmore

Posted in Uncategorized

Mt. Rushmore Road Update 2016/10/19

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Wednesday, October 19, 2016 – Work continues on Mt. Rushmore Road and the adjacent side streets. On the west side of Mt Rushmore

Posted in Uncategorized

Mt. Rushmore Road Update 2016/10/17

FOR IMMEDIATE RELEASE Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Monday, October 17, 2016 – Beginning Thursday, Oct. 20, motorists can expect Saint James Street to be closed for utility construction from the Mt. Rushmore Road

Posted in Uncategorized

Mt. Rushmore Road Update 2016/10/12

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Wednesday, October 12, 2016 – Work continues on Mt. Rushmore Road and the adjacent side streets. On the west side of Mt Rushmore

Posted in Uncategorized

Mt. Rushmore Road Update 2016/10/06

FOR IMMEDIATE RELEASE Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Thursday, October 06, 2016 – Beginning Monday, Oct. 10, motorists can expect Fairview Street to be closed for utility construction from the Mt. Rushmore Road intersection

Posted in Uncategorized

Mt. Rushmore Road Update 2016/10/05

Mt. Rushmore Road Reconstruction Project Update Project #NH 0016(79)68, PCN 027C Pennington County RAPID CITY, SD – Wednesday, October 5, 2016 – Work continues on Mt. Rushmore Road and the adjacent side streets. On the west side of Mt Rushmore

Posted in Uncategorized