Project #NH 0016(79)68, PCN 027C – Work on the large block retaining wall between South Street and Clark Street and the concrete retaining walls between Columbus Street and Fairview Street is anticipated to start again in March, 2017. Pedestrian access between Clark Street and South Street on the east side of Mt. Rushmore Road will remain closed until sidewalk and handrail installation is completed in the spring. Temporary Pedestrian Access Routes will be maintained at Fairview Street and South Street.

All lanes between Kansas City Street and Saint James Street should be open by the end of the day today. Work on the project will be suspended after traffic control is removed, until next spring. The weekly public meetings are suspended until next spring. The project is approximately 95% complete.

Project #NH 0016(84)67, PCN 049F – Construction continues from Saint Francis Street through the Saint Patrick Street intersection. The northbound lanes have been paved. Traffic in this area has been shifted to the southbound lanes of Mt Rushmore Road. The east half of the Saint Patrick Street intersection is anticipated to be opened the first week in January. Work in Saint Anne Street are not anticipated to begin until after January 1, 2017.

Weekly public meetings for this part of the Mt Rushmore Road Reconstruction project (from Saint James Street to Flormann Street) are held each Thursday at 8 a.m. at the Rushmore Hotel.

Business access on Mt. Rushmore Road will remain open at all times. Motorists are asked to slow down through the work zone and be prepared for: suddenly slowing, merging and stopped traffic, minor delays, loose gravel, uneven surfaces and bumps, as well as construction workers and equipment adjacent to the roadway.

Project information is available at http://www.mountrushmoreroad.com. For questions, the public may contact Debby Heisinger at Ferber Engineering Company Inc. by phone (605) 343-3311 or email@ferberengineering.com.

FEC
Debby Heisinger
Office Manager
729 E Watertown Street
Rapid City, SD 57701
605-343-3311
http://www.ferberengineering.com

Posted in Uncategorized

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s

%d bloggers like this: