Monthly Archives: March 2017

Mt. Rushmore Road Clarification Update 2017/03/30

RAPID CITY, SD – Thursday, March 30 – CLARIFICATION This version clarifies business access from the west half of Mount Rushmore Road, between Saint Patrick and Saint Anne streets, as the portion of the road that will have intermittent closures;

Posted in Uncategorized

Mt Rushmore Road Update 2017/03/29

RAPID CITY, SD – Wednesday, March 29 – Work on storm sewer, grading and gravel, curb and gutter, paving and lighting continues in the Saint Patrick Street to Saint Anne Street section of Mount Rushmore Road, in Saint Francis Street

Posted in Uncategorized

Mt. Rushmore Road Update 2017/03/22 027C 049F

RAPID CITY, SD – Wednesday, March 22 – Work on storm sewer continues in the Saint Anne Street to Saint Patrick Street section of Mount Rushmore Road and in Saint Francis Street from Mount Rushmore Road to the west 140-feet,

Posted in Uncategorized

Mt. Rushmore Road Update 2017/03/16 027C 049F

RAPID CITY, SD – Beginning Thursday, March 23, motorists can expect intermittent closures of the west half of the intersections of Mount Rushmore Road with Saint Cloud Street and Franklin Street for pavement removal. Saint Cloud Street will be closed

Posted in Uncategorized

Mt. Rushmore Road Update 2017/03/15 027C 049F

RAPID CITY, SD – Wednesday, March 15 – Work on storm sewer has begun in the Saint Anne Street to Saint Patrick Street section of Mount Rushmore Road. Saint Francis Street from Mount Rushmore Road to the west 140-feet, up

Posted in Uncategorized

Mt. Rushmore Road Update 049F 027C 2017/03/10

RAPID CITY, SD – Friday, March 10 – Removal work has begun at Flormann Street and is continuing to move north along Mount Rushmore Road to Saint Patrick Street. Work on storm sewer will begin in the Saint Francis Street

Posted in Uncategorized

Mt. Rushmore Road Update 2017/03/02 027C – 049F

Mount Rushmore Road Reconstruction Traffic Change Update RAPID CITY, S.D. – A shift in traffic on Mount Rushmore Road, between Flormann Street and Saint James Street, is scheduled for Wednesday, March 8. Crews will begin setting up traffic control on

Posted in Uncategorized