Mt Rushmore Road Update 2017/05/31 027C 049F

RAPID CITY, SD – Wednesday, May 31 – Work is being done on retaining walls, sidewalk, lighting, and landscape from St. Patrick Street to Flormann Street this week and next week. The west half of the Franklin Street intersection is

Posted in Uncategorized

Mt. Rushmore Road Update 2017/05/31 027C 049F

Posted in Uncategorized

Mt. Rushmore Road Update 2017/05/24 027C 049F

RAPID CITY, SD – Wednesday, May 24 – Work on curb and gutter, fillets, lighting and associated side street surfacing from St. Patrick Street to Flormann Street continues this week. Access to businesses on the west side of Mount Rushmore

Posted in Uncategorized

Mt. Rushmore Road Update 2017/05/18 027C 049F

RAPID CITY, SD – Thursday, May 18 – Work on curb and gutter, fillets, lighting and associated side street surfacing from St. Patrick Street to Flormann Street continues this week. Access to businesses on the west side of Mount Rushmore

Posted in Uncategorized

Mt. Rushmore Road Update 2017/05/10

RAPID CITY, SD – Wednesday, May 10 – Work on curb and gutter, fillets, lighting and associated side street surfacing from St. Patrick Street to Flormann Street continues this week. Access to businesses on the west side of Mount Rushmore

Posted in Uncategorized

Mt. Rushmore Road Update 2017/05/04 027C 049F

RAPID CITY, SD – Thursday, May 4 – Work on curb and gutter, fillets, lighting and associated side street surfacing from St. Patrick Street to Flormann Street continues this week. Access to businesses on the west side of Mount Rushmore