Monthly Archives: July 2017

Mt. Rushmore Road Update 2017/07/19 049F 027C

RAPID CITY, SD – Wednesday, July 19 –  Water main installation and storm sewer installation continue on Mt. Rushmore Road from Flormann Street to St Francis Street with surfacing work to follow in this area. Work is being done on

Posted in Uncategorized

Mt Rushmore Road Update 2017/07/12 027C 049F

RAPID CITY, SD – Wednesday, July 12 –  Water main installation continues on Mt. Rushmore Road from Flormann Street to St Francis Street with storm sewer installation to follow in this area. Work is being done on retaining walls, sidewalk,

Posted in Uncategorized

Mt. Rushmore Road Update 2017/07/05 027C 049F

RAPID CITY, SD – Wednesday, July 5 –  Water main installation continues on Mt. Rushmore Road from Flormann Street to St Francis Street with storm sewer installation to follow in this area. Work is being done on retaining walls, sidewalk,

Posted in Uncategorized