Mount Rushmore Road Update 2018/03/06

Project #NH 0016(84)67 PCN 049F
Pennington County

Mt. Rushmore Road Reconstruction Project to Begin March 12

RAPID CITY, S.D. – Beginning Monday, March 12, Complete Contracting, Inc. will start phase 4 work of the Mount Rushmore Road reconstruction project, from Fairview Street to Flormann Street.

Motorists are advised of lane closures of the inside median lanes at the north end of the project for work on asphalt removal, subgrade preparation, curb and gutter and stamped concrete median. Business access on Mount Rushmore Road will remain open at all times.

Work in this phase of the project includes medians, pavement markings, handrails and landscaping, with an anticipated completion date of May 2018.

The public may contact the public information specialist for more information on this project.
Ferber Engineering Company, Inc.
Debby Heisinger
Phone: (605)343-3311


Posted in Uncategorized

Leave a Reply

Fill in your details below or click an icon to log in: Logo

You are commenting using your account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: