About the Project

The Mt. Rushmore Road Reconstruction Project in Rapid City, South Dakota, was designed and has been constructed in three phases.

Phase 1 (01TH), US 16 from the end of the divided segment on the south side of Rapid City to Flormann Street, is completed.

Phase 2 (027C), Mt. Rushmore Road from Saint James Street to Omaha Street, is completed.

Phase 3 (049F) is currently being constructed. Phase 3 includes Mt. Rushmore Road from Saint James Street to Flormann Street.The construction includes Urban Grading, Storm Sewer, Curb & Gutter, Sidewalk, Lighting, Signals & PCCP Surfacing. The completion date is May 2018.