Traffic Control and Access During Construction

Access During Construction
Business access signing will be provided during construction and will be placed where they will be visible while traveling in both directions along the roadway. Driveways, streets, and roadways that enter the project will be delineated such that they are clearly visible during all hours.
During utility installation and grading work, a maximum of two consecutive side streets and intersecting roads, which are connected to a parallel street network, may be closed simultaneously. During paving operations, a maximum of three consecutive side streets and intersecting roads may be closed simultaneously with the intent that no more than every other side street would remain closed the following day. To open side streets in a timely manner, temporary gravel crossings may be utilized.